Michigan Solar 3rd Party Consultant Review
Michigan
Michigan Solar Consultant Review
American Heritage Farms
Brown Farm
Busy Bee Farms
Pletcher Family Trust
Stumpos Lane
Michigan Legislators want to meet their sustainable energy goals.
- Site Layouts + Optimization
- Permitting
- Solar Production Analysis
- Environmental
- Site Selection
- Interconnection
To reduce greenhouse gas emissions, Michigan passed legislation to expand the state’s Renewable Energy Standard. Under the new law, Michigan aims to achieve 100% clean energy statewide by 2040. Expanding and citing renewable energy resources, including solar, is key to hitting sustainability milestones. In alignment with this objective, and its own integrated resources plan, a local electric utility solicited a bid to acquire solar generation. A solar developer responding to this RFP asked our team to assess the feasibility of five potential projects in development. Our team’s assessments of these projects included several essential steps.
Project Approach
To assess the feasibility of these five solar projects, the ms team used the SROPTC method developed by NREL (National Renewable Energy Laboratories) to identify any fatal flaws. This approach focuses on six factors: Site, Resources, Offtake, Permits, Team, and Capital (SROPTC). Our team assessed each site using this method to identify any issues that could impact the project’s ability to be constructed. A summary of the key services provided follows.
Solar Production Analysis
Our team, in collaboration with a trusted engineering partner, conducted solar energy production studies at each of the five sites. Then, we used these studies in estimating the monthly average solar energy output, reviewing past and future solar irradiance, shading factors, and expected annual production at each location. The calculated values were used to validate the client’s anticipated output.
Permit Requirements
Permits for solar facility construction vary by state, county, and depend on the size of the project. The team reviewed the authority having jurisdiction (AHJ) requirements for each solar project. Permits for demolition, construction, zoning, architectural compliance, and right-of-way access were identified. We compiled this information into a permit matrix to provide the client a single document outlining AHJ contact, review timeline, and required submittals for each anticipated permit.
Site Selection Analysis
The team conducted a visual imagery to identify past and present land use. We viewed access to roadways, distance from buildings, and potential challenges from adjacent properties. Proximity to existing infrastructure was vital to ensure feasibility for transport of equipment and electrical interconnection.
Environmental
Our team provided an environmental desktop review of the constraints that may restrict project development. These constraints included environmental and community factors such as wetlands and streams, threatened and endangered species, hazardous materials, and archeological and historical information. The team reviewed plans against available data to minimize disturbance or provide a mitigation strategy.
Interconnection
Interconnection studies determine the effects of the injection of new energy generation on the existing electrical infrastructure. When solar power is generated at these sites, it will be added to the grid through the closest circuit. The additional source of energy may require upgrades to the current equipment in the area. The team reviewed the interconnection studies to ensure the developer had identified and were prepared to finance all upgrades necessary to interconnect with the utility.
A Solar-Powered Future
Upon completion of the review, all sites were found to be feasible for the proposed solar installation. As an independent reviewer, our team provided important assessments for the developer, the investors, and the stakeholders for the project.
The review also provided the developer with important information to help guide their design decisions and provide permitting insight as they progress through the development phase.
Once constructed, Michigan will be one step closer to its 100% clean energy goal.